Friday, September 16, 2005

Blog Bits

Highlights of Last Evening’s Board Meeting
The school board met in regular session last evening. The highlights of the meeting are as follows:

- The board approved monthly claims and personnel.

- The board heard a report on the school improvement plan at Washington Elementary. Mrs. Riise explained the use of the DIBELS assessment and the three-tier intervention model.

- Mrs. Riise also reported that the students at Washington Elementary have raised over $1,000 for victims of hurricane Katrina.

- The board gave permission to publish Notice to Taxpayers of Additional Appropriation from the rainy day fund.

- The next board meeting will be on October 6, 2005 at 7:00 p.m. in the Administration Building.


Construction Update
At Washington, Webster, Lincoln schools, the contractors are still working on items that have been identified on the punch list. Principals have contacted the construction manager with unresolved issues in their buildings.

At Menominee Elementary, the interior work is substantially completed. The contractors are installing the new parking lot. Projected completion of this installation is late October.

At Jefferson Elementary, the masons will complete the construction of the load bearing walls during the next two-week period. The pouring of the concrete floors will begin. Trusses are scheduled to arrive on site on November 1st. The new addition should be under roof by the end of November.

At Plymouth High School, the music wing is moving closer to completion. Carpeting has been installed in three of the large instructional areas. Vinyl floor covering will be installed in the choir room next week. Work on the driveway around the music wing is nearing completion. Weather permitting the base coat of asphalt will be applied in another week. The target date for completion of the music wing is October 1. The contractors have completed the electrical rough-ins in the cafeteria area. Wall board is being installed at this time. Target completion date of the cafeteria is November 1. The masons are wrapping up their work in the multipurpose wing. Mechanical, plumbing and electrical workers are installing their equipment. Electrical rough-ins have been completed in the broadcast classroom and studio. Contractors are installing wall board. During the next two week period, painting and installation of ceiling grids will begin in that area.

The construction of the load bearing walls continues in Section A of the new elementary. This process will continue during the next two weeks. All the footers and foundations in the classroom wing will be completed next week.

ISTEP
Students in the Plymouth Community School Corporation will be taking the ISTEP tests next week. Please be sure your children are getting plenty of sleep and a good meal each morning