Thursday, April 07, 2005

Construction Update

A construction meeting was held on April 7, 2005 @ 9:00 a.m.

During the past two weeks:
The interior masonry at Washington and at the Lincoln kitchen is 95% complete. The framing of the roof has been completed at Webster. The interior footings have been poured on the music wing at Plymouth High School and work has continued on the bearing walls in the music wing. The footers have been poured and the foundation walls are being formed at this time in the multi-purpose room area.

During the next two weeks:
The interior masonry work at Lincoln and Washington will be completed. The cement slab will be completed in the music area at Lincoln. The footers and foundations will be completed for the dry storage area at Lincoln. The slab at Webster is scheduled for pouring on the 22nd of April. The metal decking on the roof at Webster will be started Monday and completed within two weeks.

At Plymouth High School, the construction of the interior walls in the music wing will continue. The bar joist over the corridor in the music wing will be installed tomorrow. Work will continue on the foundations in the multi-purpose area.

Gas Shut-off:
The gas will be shut off at Washington by NIPSCO for a short period of time during the spring. This will be done after the heating season and Mrs. Riise will be notified. This should not interfere with schooling in that building.


The next meeting is scheduled for the 21st of April.