A construction meeting was held Thursday morning, August 25, 2005, at 9:00 a.m.
Webster, Washington, and Lincoln Junior High
Contractors are following-up on punch list items that were created by the architect or reported by building principals to the construction manager. This process will continue for the next few weeks.
Plymouth High School
The cabinetry is being installed in the instrument and uniform storage areas. The rough-in plumbing in the new restrooms of the music wing has been completed. Masons are following right behind. The sidewalks and curbs are being installed around the music wing. The new west entrance has been secured with new doors. The steel joists over the multi-purpose room were installed this morning. The roofers will complete the roof over the music wing and then move to the multi-purpose wing. Mechanical and plumbing contractors will continue their work throughout both wings. The new speech practice rooms have been dry walled and are scheduled for painting tomorrow. The installation of cabinetry in the costume storage area has been completed. During the next two week period floor covering, lighting fixtures, and ceiling pads will be installed in that area. The broadcasting area has been framed. Electricians are completing the electrical rough ins.
Jefferson Elementary
The plumbing and electrical rough-ins have been completed. The masons are scheduled to mobilize next week.
New Elementary
The contractors are pouring footers and installing foundation walls in Section B, the classroom area. Masons are continuing to build walls in Section A.
This reminder – the south parking lot at Plymouth High School will be closed Saturday for re-lining.