Construction Update

Jefferson Elementary - the two rooms undergoing renovation have been painted. Once the floor coverings are installed at Menominee, those persons will move to Jefferson and complete installation of the floor coverings at that location.

The footers and foundation walls are completed. Plumbers and electricians are in the process of installing the plumbing and electrical rough-ins.

Menominee Elementary – the vinyl tile has been installed in the new science room. The installation of the lockers has begun. The installation of carpet in the new music room began this morning. Once the carpet is installed, the vinyl mop board will be put in place in all rooms. Menominee, for the most part, is completed. We have possession of all the rooms except the new music room.

Washington Elementary – Carpet has been installed in both of the new special education rooms. Workers are installing the tile in the cafeteria. The ceiling grid is going up in the storage room, the nurse’s office and conference room. Electricians are installing light fixtures. Plumbers have installed most of the fixtures with the exception of the sinks in the nurse’s office and the special ed rooms. Once the installation of the tile is completed in the cafeteria, the carpet in the hallways, teacher work room and lobby will be installed. The plastering in the overhang is being completed this week.

Lincoln Junior High – Punch lists have been developed for the band and choir room. Final hook-ups are being made in the kitchen. The final preparation of wall board is being completed in the new nurse’s office. Painting will begin tomorrow. Ceiling grid will also be installed tomorrow in the nurse’s office. Cabinetry will be installed late this week in Miss Gilbert’s room and in the nurse’s office.

Plymouth High School – Workers are completing the masonry in the north entrance. Concrete is scheduled to be poured late this week in that area. Cabinetry is being installed in the music wing. Electrical rough-ins are in process in the new broadcast classroom, the speech practice rooms, and the music wing. Possession of rooms in the music wing will begin in mid to late September with all being occupied by October 1st.
The New Building Site – Work continues on the installation of footers, foundation walls, and block masonry walls. The water line and sanitary sewer are being installed at this time