A construction meeting was held on March 10, 2005 @ 9:00 a.m.

During the past two weeks:
The brick on the Lincoln locker room and the roofing on the Lincoln locker room are near completion. The underpinning at Lincoln in the kitchen, choir room, and band room has been completed.

The brick on the Washington south addition is 50% completed. The roofing at Washington is completed on the north addition. The south addition will be completed by the end of today.

Temporary heat is on in the Washington additions. The plumbing underground in the Washington kitchen area was started. The masonry at Webster is 70% complete. Approximately 100 feet of the pre-cast panels has been removed on the west side of Plymouth High School.

During the next two weeks:
A slab will be poured on grade in the Lincoln music, choir, kitchen, and locker room areas. The slabs will be poured on the north addition at Washington and in the cafeteria portion of the south addition. As soon as the rough-ins are completed in the kitchen area, the slabs will be poured there. The brick on Washington north will be completed.

The bearing walls at Webster will be completed on Monday. The roof trusses will be delivered tomorrow and set next week. The interior walls at Lincoln and Webster will be started.

REMINDER – Power Shut-off:
During spring break, the electricity will be off at Lincoln on Monday and Tuesday. The electricity at Washington will be disconnected on Wednesday and Thursday. The front entrance of Washington will be unaccessible during spring break due to the bricking of the west wall of the north addition. All schedules are contingent on the weather.

Last Project milestone dates:
Washington, Lincoln and Webster – new construction including kitchens to be completed by June 15, 2005. The high school west addition to be completed by July 29, 2005. The Washington and Lincoln renovations completed by July 29, 2005. The high school multi-purpose addition to be completed by December 1, 2005. The high school renovations will start May 31, 2005 and be completed by December 1, 2005.