Tuesday, May 17, 2005

Construction Update

A construction meeting was held on May 12, 2005 @ 9:00 a.m.

During the next few weeks:
At Lincoln, the ceiling grid will be completed in the kitchen. The installation of the quarry tile, exhaust hoods, and light fixtures in the kitchen area will be completed. The foundation and masonry for the dry food storage area will be completed. The drywall will be finished and painted in the music and choir rooms. The ceiling grid in the music and choir rooms will be installed. The ceiling will be plastered in the new locker room.

At Washington, the ceiling grid, light fixtures, exhaust hoods, and quarry tile will be installed in the kitchen. Drywall will be laid in the bulk head in the cafeteria. The windows will be installed in both additions. New aluminum entrances into the cafeteria area will be installed.

At Webster, the interior masonry will be completed. Walls will be painted. The parameter fascia and soffit and gutters will be installed. The roof will be shingled. The ceiling grid and light fixtures will be installed throughout. The aluminum entrances will be put in place.

At PHS in the new music wing, the block walls will be completed, the bricking will begin, all the floors will be poured, the mezzanine steel will be set, and the construction of the roof will begin. The masons will continue to block in the multi purpose room.

At the new elementary site, grading will begin and the pad will be established for the new building.

At the conclusion of the last teacher day, the demolition of the walls in the cafeteria and kitchen area will begin at Washington elementary. The relocation of utilities at Jefferson Elementary will take place. The grading for the new parking lot at Menominee will begin. The demolition of the stage area in the cafeteria at the high school will begin.

The next construction meeting will be next Thursday, May 26, 2005 at 9:00 a.m.