Thursday, February 24, 2005

Construction Update

A construction meeting was held on February 24, 2005.

During the past two weeks:
The steel was installed at Webster. The masonry work is started on the perimeter walls and the block was laid along the new hallway. The installation of the underground plumbing at the Lincoln kitchen is still underway. The Lincoln kitchen electric rough-in is still in progress. The soil removal in the music and choir rooms at Lincoln is completed. The joists and decking is completed at Washington and has started at Lincoln. The roofing on the north addition at Washington is completed. The perimeter foundations on the music addition at the high school are sixty percent (60%) complete. The underground plumbing at Plymouth High School has been started.

During the next two weeks:
The installation of the veneer brick continues on the Washington north addition. The roofing will be completed on Washington south. Temporary heat will be started in both areas. The load bearing walls will be constructed at Webster. The veneer brick will be completed on the locker room addition at Lincoln Junior High. The roof will be completed and temporary heat will be started in the locker room addition. The slab on grade in the kitchen and choir room will be installed. At Plymouth High School, the installation of the interior foundations will begin. Contractors will take down the pre-cast on the west wall of the high school.

Power shut-off:
On Monday of spring break the power will be shut off for three to four hours at Plymouth High School. On Tuesday and Wednesday of spring break, power will be shut down at Lincoln Junior High. The power will be shut off at Washington during the week of spring break.

Project milestone dates:
Washington, Lincoln and Webster – new construction, including kitchens to be completed by June 15, 2005. The high school west addition to be completed by July 29, 2005. Washington and Lincoln renovations to be completed by July 29, 2005. The high school multi-purpose room addition to be completed by December 1, 2005. High School renovations begin May 31, 2005 and are to be completed by December 1, 2005.